Installation
900684-01 06/2018
Innovative Hearth Products
DRT3000 Series Direct-Vent Gas Fireplaces
17
INSTALLATION SEQUENCE
The typical sequence of installation is outlined below; however, each installation is unique and may result in
variations to the steps described.
See the pages referenced in the following steps for detailed instructions.
Framing
1. Construct the Fireplace Framing
(
Page 17
)
.
2. Prepare the Fireplace Top Spacers
(
Page 19
)
.
3. Route the Gas Supply Line to the Fireplace
(
Page 19
)
.
4. Determining Vent Setup in the Combination Venting Unit
(
Page 20
)
5. Installing Non-Combustible Front Standoff
(
Page 21
)
6. Rough in the Electrical Supply, if Needed
(
Page 21
)
.
7. Install the [Optional] Blower Kit before Installation in the Framing
(
Page 21
)
.
Venting
8. Place the Fireplace in the Framing and Secure
(
Page 22
)
.
9. Select a Horizontal or Vertical Vent System
(
Page 22
)
.
10. Install the Vent Restrictor (if necessary)
(
Page 23
)
.
11. Install the Vent System
(
Page 26
)
.
Electrical Connection
12. Complete the Field Wiring
(
Page 38
)
.
13. Install the [Optional] Blower Kit after Installation in the Framing
(
Page 40
)
.
Gas Connection
14. Connect the Gas Line
(
Page 41
)
.
15. Verify Proper Fireplace Operation
(
Page 42
)
.
Finishing
16. Optional: Install the Firebox Liners
(
Page 43
)
.
17. Install the Logs, Volcanic Stone, and Glowing Embers
(
Page 43
)
.
18. Install the Glass Door
(
Page 43
)
.
19. Adjust the Air Shutter to Ensure Proper Flame Appearance
(
Page 43
)
.
20. Install the Hood in Traditional Fireplaces
(
Page 44
)
.
21. Reinstall the Included Barrier
(
Page 45
)
.
22. Install the Finishing Materials
(
Page 45
)
.
23. Attach the Safety-in-Operation Warning Labels
(
Page 45
)
.
24. Installing Batteries for Backup and Wall Switch
(
Page 45
)
.
1.
Construct the Fireplace Framing
1.
Frame the fireplace as illustrated in
Table 10
. For corner framing installations, use
Table 11
. All framing details
must allow for a minimum clearance to combustible framing members as shown in
Table 8
.
2.
If the fireplace is to be elevated above floor level, a solid continuous platform must be constructed below the fireplace.
NOTE:
Headers may be in direct contact with the fireplace top standoff spacers when they are bent up vertically,
maintaining the 4” clearance to the fireplace top, but must not be supported by them or notched to fit around them.
All construction above the fireplace must be self-supporting. DO NOT use the fireplace for structural support.