5.11. Generator & Battery Page
To configure battery charging settings, click on the BATTERY icon and then on ‘Batt Charge’.
What this page displays:
Generator start voltage/SOC %.
Grid power start voltage/SOC %.
Float V is the voltage at which a battery is maintained after being fully charged.
Absorption V the level of charge that can be applied without overheating the battery.
Float V for an AGM battery is 55.20V.
Absorption V is for an AGM battery is 57.60V.
Equalization V for an AGM battery is 58.80V.
Equalizing charge/overcharge to remove sulphate crystals that build-up on the plates over
time on lead-acid batteries.
What you can do from this page:
Tick ‘Gen Charge’ to charge the batteries from the gen I/P.
Tick ‘Grid Charge’ to charge the batteries from the grid I/P.
Tick ‘Gen Signal’ signal to auto-switch a relay box.
Tick ‘Grid Signal’ signal to auto-switch a relay box.
Do not alter these settings too many times on the same battery as it may damage
the battery.
Summary of Contents for SUN-25K-SG01HP3-EU-BM2
Page 19: ...Page 19 Hybrid Inverter Installer Manual 4 4 1 Function Ports Definition ...
Page 26: ...Page 26 Hybrid Inverter Installer Manual ...
Page 27: ...Page 27 Hybrid Inverter Installer Manual ...
Page 29: ...Page 29 Hybrid Inverter Installer Manual 4 10 Wiring System for Inverter ...
Page 30: ...Page 30 Hybrid Inverter Installer Manual 4 11 Wiring Diagram ...
Page 31: ...Page 31 Hybrid Inverter Installer Manual ...
Page 32: ...Page 32 Hybrid Inverter Installer Manual 4 12 Typical Application Diagram of Diesel Generator ...