Electrical Connection
5
39
5.6.3
AC Wiring Procedure
Assignment of AC cables should be paid attention to, especially “PE” wire.
Step 1:
Assemble AC cables to connector supplied. See “5.6.2 Assembling AC
Cables to Connector”.
Step 2:
Make sure that the AC circuit breaker is disconnected and DC switch is
rotated to the “OFF” position.
Step 3:
Connect phase cables and “N” cable to AC circuit breaker.
−
Plug AC connector to corresponding AC terminals.
−
Screw AC cables except the “PE” cable to the AC circuit breaker.
Step 4:
Connect AC circuit breaker to utility grid.
Step 5:
Make sure that all AC cables are firmly installed.
Summary of Contents for SG1K5TL-31
Page 1: ......
Page 2: ......
Page 7: ...1 SAFETY AND PRODUCT INFORMATION FOR INSTALLER AND USER...
Page 8: ...2...
Page 21: ...15 INSTALLATION AND MAINTENANCE INFORMATION ONLY FOR INSTALLER...
Page 22: ...16...
Page 57: ...51 OPERATION INFORMATION FOR INSTALLER AND USER...
Page 58: ...52...
Page 74: ...SG1K5TL 31 User Manual 68...