56
To navigate through the complete parameter list, complete the following:
1.
Turn the control knob and select ‘Complete parameter list.’
2.
Press the control knob.
3.
The ‘Complete parameter list’ opens – the title of the first parameter list page is preselected.
4.
Press the control knob and select the title of the parameter list page.
5.
Turn the control knob and go to additional technology topics.
6.
Press the control knob to only preselect the topic.
7.
Turn the control knob to preselect to the right of the title “Current page of total.”
8.
Press the control knob to select “Current page of total.”
9.
Turner the control knob within a topic to go to other parameter list pages.
10.
Go to the work area to make the settings or exit the parameter list pages with “Back.”
Start Commissioning Wizards
You can start the commissioning wizard at any time via the menu items described below and benefit from the
structured processing of commissioning parameters.
To access the commissioning wizard, go to the adjust / repair page
and
using the control knob, select “Commissioning wizard.”
Refresh Operator Unit
The list entry “Refresh operator unit” is displayed if changes are made on the “Complete parameter list” or the
“commissioning wizard” that impact the device pages.
Backup Present Views:
-
The device checks at the start of each minute whether the configuration has changed that im-
pacts the device pages. Wait for the device clock to advance to the next minute after exiting
“Complete parameter list” or the “Commissioning wizard.”
-
If a change is made to the configuration of a operator unit that relates to the entire plant (e.g.
heat circuit 1 “On”), all devices on the plant must be updated prior to hand off to the end user.
Summary of Contents for S-ASX 30
Page 2: ...2 ...
Page 24: ...24 10 CORRECTIVE FACTORS 10 1 Heating Performances ...