Preparing to Install a System
Site Planning for ftServer V 2302, V 4304, and V 6308 Systems
1-7
❏
Have you created a sketch of how you plan to arrange the system at the installation
site? Consider the available cable lengths, the placement of external devices, and
the location of network and voice communication connections.
On the sketch, show the following:
Location of the system and its external components
Power cords, and telephone and interface cables
Locations of AC power receptacles, phone jacks, Ethernet jacks, switches, and
hubs
N O T E
Make sure that all cords and cables are long enough to
reach between their respective components and
connectors. Route all cables out of the way of foot traffic.
Working with Other Groups
❏
Have you provided your facilities group and contractors with the sketch of how you
plan to arrange the system and copies of the following?
“Redundant Power Sources” on page 3-1
Appendix B, “Electrical Circuit and Wiring Information”
Any notes you have about site planning
❏
Have you reviewed and discussed the requirements with the facilities personnel
and contractors to ensure that all site modifications are understood and
implemented?
If you have any questions about the number and types of components, contact your
Stratus account executive or distributor.
Preparing to Install a System
To prepare for the installation of a system by a field engineer, perform the following
tasks:
1. Complete all site preparation work, as described in
“Preparing to Take Delivery of
.
2. Take delivery of the system.
3. Move the system to its installation site, as described in
Installation Site” on page 1-8
.