Power Outlet Requirements
Electrical (AC) Power Planning
4-5
Power Outlet Requirements
If you use a pair of PDUs in the cabinet, use Tables
to determine the total
number of power outlets required outside the cabinet.
1. In the Quantity column, write the number of each type of component.
2. Multiply the value in the Quantity column by the value in the Outlets column, and
enter the total in the Subtotal column.
3. Add the values in the Subtotal column and enter the sum next to TOTAL NUMBER
OF EXTERNAL POWER OUTLETS.
Table 4-6. Worksheet for Determining B-Side Power Requirements
System Component
Quantity
@ Power
(Watts)
AC Power
(Extended)
ftServer 6600 system
x
900
=
ftServer 5600 system
x
650
=
ftServer 3300 system
x
500
=
x
300
=
TOTAL B-SIDE POWER REQUIREMENTS
Table 4-7. Worksheet for Determining External Power Requirements
System Component
Quantity
@ Power
(Watts)
AC Power
(Extended)
and V115 keyboard
and mouse
x
30
=
x
21
=
x
56
=
External modem power transformer
x
5
=
User-supplied components
TOTAL EXTERNAL POWER REQUIREMENTS
Summary of Contents for ftserver 3300
Page 1: ...Stratus Technologies R553 01 Stratus ftServer 3300 5600 and 6600 Site Planning Guide...
Page 14: ...Preface xiv Stratus ftServer 3300 5600 and 6600 Site Planning Guide R553...
Page 24: ...System Documentation 1 10 Stratus ftServer 3300 5600 and 6600 Site Planning Guide R553...
Page 32: ...Planning for Cables 3 4 Stratus ftServer 3300 5600 and 6600 Site Planning Guide R553...
Page 50: ...Stratus Supplied Power Cords 4 18 Stratus ftServer 3300 5600 and 6600 Site Planning Guide R553...
Page 133: ...Standards Compliance Standards Compliance D 3 VCCI Note BSMI Note...
Page 134: ...Standards Compliance D 4 Stratus ftServer 3300 5600 and 6600 Site Planning Guide R553...
Page 138: ...Index Index 4 Stratus ftServer 3300 5600 and 6600 Site Planning Guide R553...