Installation Area

The installation area should be free of sources of vibration and electromagnetic interference that could 
affect the proper functioning of the printer.

The floor gradient should be less than 0.5% (5 mm per meter).

The floor should be stable and able to bear the load of the printer. The minimum floor load is 630 kg/m

2

 

(129 lb/ft

2

).

The server workstation and the printer should be located in the same room.         

The cable between the server workstation and the printer should not exceed 5 meters (16 feet). The 
communication cable provided should not be extended or replaced with a longer cable.

Clearance around and above the printer should ensure convenient access and servicing.         

The area around the printer should remain dry at all times. Do not place the cleaning station within 
5 meters (16 feet) of the printer.

Shelves and cabinets are recommended near the printer for convenient storage of tools, parts, 
accessories, manuals, and materials.

Floor Plan (Printer Area)

The following is a sample floor plan, showing the 3D printing system—the printer, the materials cabinet, 
and the workstation. The dimensions shown in the figure  are the minimum clearance requirements.

Figure 4   Printer floor plan (sample, not to scale)

Stratasys J826

Installation Area

DOC-18005 Rev. E

©

2019-2020 Stratasys. All rights reserved.

10

Summary of Contents for J826

Page 1: ...DOC 18005 Rev E 3D Printing System Site Preparation Guide Stratasys J826...

Page 2: ...he implied warranties of merchantability and fitness for a particular purpose It is the responsibility of the system owner material buyer to determine that Stratasys material is safe lawful and techni...

Page 3: ...1 Electrical Requirements 12 Power 12 Grounding 12 Circuit Breaker 13 Residual Current Device RCD 13 Power Connection 13 UPS Uninterrupted Power Supply 13 Communication Lines 15 Local Area Network 15...

Page 4: ...Cleaning Solvent 19 Site Preparation Checklist 20 DOC 18005 Rev E 2019 2020 Stratasys All rights reserved 4...

Page 5: ...st be met before the installation date The Site Preparation Checklist should be submitted to your Stratasys representative Shipping will be arranged after the checklist is received by Stratasys Non co...

Page 6: ...D cm W H D inch Weight kg lb Printer 87 120 73 5 34 2 47 2 29 234 kg 516 lbs Materials cabinet 67 x 110 x 64 26 4 x 43 3 x 25 2 152 kg 335 lbs Table 1 Size and weight W Width H Height D Depth The dept...

Page 7: ...ill advise regarding these matters Note Only Stratasys certified Customer Support Engineers are authorized to unpack and install equipment supplied Shipping Pallet The following table shows the approx...

Page 8: ...e printer The installation location must be accessible from the unloading area The customer is responsible for unloading the printer from the truck and transferring it to the installation location Min...

Page 9: ...Figure 3 Printer center of gravity Stratasys J826 Shipment and Delivery DOC 18005 Rev E 2019 2020 Stratasys All rights reserved 9...

Page 10: ...t be extended or replaced with a longer cable Clearance around and above the printer should ensure convenient access and servicing The area around the printer should remain dry at all times Do not pla...

Page 11: ...quirements To view the specifications for client workstations go to http help grabcad com print system requirements Stratasys J826 Workstation Requirements DOC 18005 Rev E 2019 2020 Stratasys All righ...

Page 12: ...0 240 VAC 50 60 Hz 7 A 1 phase Printer short circuit rating 1000 A If the power at the facility does not support the above specifications contact your Stratasys specialist Important The diagram below...

Page 13: ...electrician The following electrical outlets are required one outlet behind the printer three outlets close to the printer for the workstation monitor and servicing equipment UPS Uninterrupted Power...

Page 14: ...PS systems meet the above requirements Eaton PW9130G3000T 220 240 VAC Eaton PW9130L2000T XL 100 120 VAC 1Single phase 50 60 Hz 2Defined as the input to output ratio of the UPS 3UPS units that only con...

Page 15: ...shown in the following diagram Figure 6 Network installation The connection to the local network should be established prior to printer installation Telephone A telephone near the printer is recommen...

Page 16: ...and relative humidity should not exceed the limits listed in the table below Range Temperature 18 C to 25 C 64 5 F to 77 F Relative humidity 30 70 non condensing Table 6 Room temperature and relative...

Page 17: ...k of the printer and connected to an external ventilation fan with a duct air expelled from the printer is discharged directly outdoors as shown in the figure below Required Suction at the Exhaust Ada...

Page 18: ...ter oil trap must be installed on the air gun used for cleaning the printer The recommended air pressure is 5 7 bar 70 90 PSI Fire Safety Equipment A gas based fire extinguisher is recommended in case...

Page 19: ...nts for handling and storing specific materials appear in the Material Safety Datasheet MSDS included with each material Note Non compliance with these recommendations might result in reduced shelf li...

Page 20: ...cribed in this document Fill in the information requested in the checklist and submit it to your Stratasys representative An installation date will be scheduled after the checklist has been approved b...

Page 21: ...www stratasys com ___ THE 3D PRINTING SOLUTIONS COMPANY ISO 9001 2008 Certified...

Reviews: