IM-P537-01
EMM Issue 1
19
Pressurised Thermophysical deaerator with operator manual for the control unit
3.2 Handling, positioning and fastening
Step 1
Lift and unload the equipped tank body from the articulated lorry (as shown in the figure), using a crane or
suitable authorised handling system and then anchor the tank saddles (using anchor bolts) to the existing
structure.
During this lifting operation, make sure that the crane arm's opening range and the surrounding area are
free of any obstacles or the presence of unauthorised personnel.
Warning
For the lifting operation, make sure to hook the handling ropes to the two lifting eyebolts
(indicated by orange arrows).
All the operations described above must be carried out only by qualified personnel,
respecting all the rules and using the safety devices required by law.