1-22 (E)
MAV-70
2.
Connect the MAV-70s with cables.
ID Setup
Set the ID switches of the BKMA-7040s that are connected to the MAV-70s, starting from 1 to 2, 3, and 4
in order.
n
Setting the ID switch at 9 or higher is invalid.
1-15-2. Setting Up the Menu
If the MAV-70 is the master unit for capacity expansion
Set “Master” in the MAV-70 as follows.
1.
Open the “System Setup: Configuration display” menu.
2.
Select “Master” using the
and
buttons and press the
[ENTER]
button.
3.
Select “Reset” using the
and
buttons and press the
[ENTER]
button.
If the MAV-70 is used for applications other than capacity expansion
Set “Single” in the MAV-70 as follows.
1.
Open the “System Setup: Configuration display” menu.
2.
Select “Single” using the
and
button and press the
[ENTER]
button.
3.
Select “Reset” using the
and
button and press the
[ENTER]
button.
4.
Set up the other MAV-70s in the same manner.
If capacity expansion (loop connection) is implemented
BKMA-7040
BNC cables
BKMA-7040
for copying
BKMA-7040 for
capacity expansion
BKMA-7040
IN OUT
IN OUT
IN OUT
REMOTE1
BKMA-7040
IN OUT
Copy connection
Master unit (ID = 1)
Expansion unit (ID = 2)
Expansion unit (ID = 3)
Loop
connection
From host
controller
ID switch
n
The system does not run if the BKMA-7040 for copying is
installed into the expansion unit.