Commissioning | 6
KD-492 | 22320 | EN | X02
33 / 40
Illustration 22: Settings page
6.5 Testing backup operation
1. Simulate a grid outage
Switch the main fuses in the building off, so that the Backup-Box and storage system
are no longer connected to the public electrical grid. The storage system switches to
backup operation after switching off the fuses.
2. Activate a consumer in the backup circuit
Activate a consumer connected to phase L1.
3. Check backup power supply
Backup operation operates properly when the consumer connected to phase L1 is receiv-
ing electrical power and the sonnen Eclipse on the Backup-Box lights up white.
If the backup operation does not work:
Check the electrical wiring (see Electrical installation [P. 17]).
Contact sonnen customer service if the problem cannot be resolved.
6.6 Filling in the commissioning report
The commissioning report needs to be filled in for the initial commissioning.
Complete the commissioning report in the appendix of the document in full.
Make a copy of the filled in commissioning report, the original remains with the oper-
ator.
Send a scan of the commissioning report to the following e-mail address within 5 work-
ing days: [email protected] and [email protected]