The wall or stand hanging the inverter should meet conditions below:
1) Solid brick / concrete, or strength equivalent mounting surface;
2) Steel material of sufficient thickness;
3) Inverter must be supported or strengthened if the strength of wall/stand isn’t
enough. (such as the wall covered by thick layer of decoration)
4) Wooden wall with studs spaced at 12, 16, 20, 24, 28 and 32 inch.
5.2.2 Installation Carrier Required
Install the inverter at a maximum back tilt of 5 degrees and avoid forward tilted,
excessive backward tilted, side tilted or upside down.
5.2.3 Installation Angle Required
To ensure good heat dissipation and convenient disassembly, the minimum
clearance around the inverter shall not be less than the following values, as shown
in the following figure. The height above the ground marked below is
recommended assuming that three BATs are mounted.
If less or more BAT is
mounted, please lower or increase the height accordingly. (the height of one BAT is
about 300mm)
5.2.4 Installation Space Required
For multi-inverter installation, please reserve the space of
19.68 in. (500 mm)
at
least between each left and right inverter and at least
19.68 in. (500 mm)
space
from the ceiling and 51.18 in. (1300
mm) above the ground. If multiple inverters are
mounted in areas with high ambient temperatures, increase the clearances
between the inverters and ensure an adequate fresh-air supply if possible.
≥
19.68 in. (500 mm)
≥
19.68 in.
(500 mm)
≥
19.68 in.
(500 mm)
≥
19.68 in.
(500 mm)
≥
51.18 in.
(1300 mm)
Mechanical Installation
Mechanical Installation
21
20
≥
51.18 in.
(1300 mm)
≥
19.68 in.
(500 mm)
≥
19.68 in.
(500 mm)
≥
19.68 in.
(500 mm)