5 Installation
5.7 Dismantle upper cover
►
Loosen the 4 screws
►
Lift the cover on the right-hand side and remove
it.
Abb. 2-8
5.8 Establish RLU connection (optional)
►
Feed the aluminium hose into the boiler at ope-
ning
2
or
3
and fit it at connection
1
.
Abb. 2-9
Boiler-controlled room air damper in the RAI line
(optional)
Function: When the burner is switched off, the dam-
per closes to prevent any exchange of air inside the
RAI line.
Abb. 2-10: Control of a room air damper
►
Connect the room air damper on the boiler power
element to X6 (230 V AC).
►
For the parameter
Reserve relay
, select the
value
External boiler
.
The parameter
Reserve relay
is located in the
Ser-
vice menu
>
External boiler
.
5.9 Establish the chimney connection
See instructions for execution
5.9.1 Flue gas pipe: Hole for emission mea-
surement
►
Make the hole for the emission measurement
according to the following images (recom-
mendation according to standard).
►
If these specifications cannot be implemented,
then make the measuring point after a calming
section, i.e. after the longest straight section of
the pipe. The tube orientation (horizontal, ver-
tical, oblique) plays no role in this case.
►
In any case, place the measuring point before
any existing draught limiters.
You can find the function for carrying out the emission
measurement in the boiler operation manual,
keyword:
Chimney sweep function.
Installation manual
ecotop-zero, ecotop-light
19