![SolarEdge StorEdge SE7600A-US1 Installation Manual Download Page 85](http://html1.mh-extra.com/html/solaredge/storedge-se7600a-us1/storedge-se7600a-us1_installation-manual_1313757085.webp)
3. Select
Communication
è
RS485-1 Conf
è
Device Type
è
Multi Devices
. A list of devices is
displayed.
D e v i c e T y p e < M L T >
M e t e r 1 < - - - >
M e t e r 2 < - - - >
M e t e r 3 < - - - >
B a t t e r y 1 < - - - >
B a t t e r y 2 < - - - >
If an RGM is installed, it is pre-configured to Meter 1:
D e v i c e T y p e < M L T >
M e t e r 1 < W N , 1 >
M e t e r 2 < - - - >
M e t e r 3 < - - - >
B a t t e r y 1 < - - - >
B a t t e r y 2 < - - - >
4. Select
Meter 2
. The meter configuration screen is displayed (SolarEdge meters are pre-configured to
Device ID 2):
D e v i c e T y p e < M T R >
P r o t o c o l < W N >
D e v i c e I D < 2 >
C T R a t i n g < 0 >
M e t e r F u n c . < N o n e >
T o p o l o g y < W y e >
5. Configure the meter:
a. Select
Device Type
è
Revenue Meter
b. Select
Protocol
è
WattNode
c. Verify that
Device ID
is set to
2
.
d. Set the CT value that appears on the CT label:
CT Rating
è
<xxxxA>
.
If CT resets to 0, check the communication as described in step b of verify the connection:below.
e. For a meter installed at the grid connection point select
Meter Func.
è
Import.
E x p o r t + I m p o r t
E x p o r t
C o n s u m p t i o n
P r o d u c t i o n
E x t . P r o d u c t i o n
I m p o r t
N o n e
f. The selected option is displayed in the RS485 Conf screen as <E+I>.
g. Select the grid
Topology
(
WYE
or
Delta
).
Chapter 10: System Configuration
SolarEdge
-
StorEdge Installation Guide MAN-01-00262-1.3
83