RS485 Bus Configuration
To connect to the monitoring platform:
1. Designate a single inverter as the connection point between the RS485 bus and the
monitoring platform. This inverter will serve as the leader inverter.
2. Connect the leader to the monitoring platform via the LAN option (refer to ) or any
of the other options.
To configure the RS485 bus:
All inverters are configured by default as followers. To configure the leader:
1. Verify the ON/OFF/P switch is OFF.
2. Verify that AC is on.
3. Use SetApp to access the
Commissioning
menu screen as described in
4. From the
Commissioning
menu tap
Site Communication
.
5. Select the following to configure the connection:
RS485-
1
> Modbus (Multi-Device)
RS485-
1
> SolarEdge >
SolarEdge Leader
RS485-
1
> Follower Detect
The system starts automatic detection of the follower inverters connected to the
leader inverter. The inverter should report the correct number of followers. If it does
not, verify the connections and terminations.
6. To check the follower IDs and last communication time, select
RS485-1
>
Follower
List
.
7. Verify the connection of the leader to the monitoring platform, as described below.
Verifying the Connection
After connecting and configuring a communication option, perform the following
steps to check that the connection to the monitoring server has been successfully
established.
1. Go to
Commissioning > Status
.
2. In the Summary section, under
Server Comm.
, make sure
S_OK
is displayed
together with the selected communication option.
3. Scroll down to the
Communication
section and check that the communication
options are as required.
Chapter 6: Setting Up Communication to the Monitoring Platform
49
Three Phase System MAN-01-00505-1.5
Summary of Contents for Delta E30K-RW00IBNJ4
Page 84: ......