3. When the activation is complete, do one of the following:
Select
Connect to Another Device
to continue activating additional inverters.
Select
Start Commissioning
for pairing and other system configuration.
Step 2: Commissioning and Configuring the
Installation
This section describes how to use the SetApp menus for commissioning and
configuring the inverter settings.
Menus may vary in your application depending on your system type.
To access the Commissioning screen:
Do one of the following:
During first time installation: Upon activation completion, in the SetApp, tap
Start
Commissioning
.
If the inverter has already been activated and commissioned:
If not already ON - turn ON AC to the inverter by turning ON the circuit breaker
on the main distribution panel.
Open SetApp and follow the on-screen instructions (scan the inverter QR code,
move the ON/OFF/P switch to P position for 2 seconds and release).
The mobile device creates a Wi-Fi connection with the inverter and displays the
main Commissioning screen.
Setting Country, Grid and Language
The inverter must be configured to the proper settings in order to ensure that it
complies with the country grid code and functions.
1. From the
Commissioning
screen select
Country & Grid
.
2. From the
Country & Grid
drop-down list, select the required option and tap
Set
Country & Grid
.
3. From the
Language
drop-down list, select your language and tap
Set Language
.
Pairing
1. From the
Commissioning
menu, select
Pairing
.
2. Tap
Start Pairing
.
3. When Pairing Complete is displayed, the system startup process begins:
Three Phase System MAN-01-00505-1.5
34
Step 2: Commissioning and Configuring the Installation