7
rev.1011 MKTG-IM-TP
-34
-002
Installation and Owner’s Manual | TP Series Solar LED Lighting System
2.5 Drilling Mounting and Access Holes in Pole
1.
Drill thru .87” diameter holes for B.E. mounting in desired location using B.E.
Channel as guide.
2.
Drill thru one side a 1.25” access hole for PV and Luminaire connectors 4.25”
below top B.E. Channel hole (Figure 6).
3.
Determine desired location of fixture arm and drill mounting holes for fixture arm
by using arm bracket as template (Figure 7).
4.
Drill access hole to route Luminaire wiring to B.E. Enclosure (Figure 7a). Sol will
provide template for concrete pole manufacturing.
5.
Secure arm with 2x 5/8-11 x 10” bolts.
For Wood or Concrete Poles A separate addendum will be provided
for each. Contact Sol if you are installing a wood or concrete pole.
FIGURE 7a
DRILL TEMPLATE - ARM
FIGURE 6
DRILLING B.E. MOUNT & ACCESS HOLES
FIGURE 7
DRILLING FIXTURE ARM
MOUNTING & ACCESS HOLES
Helpful Hint#1:
If mounting two
arm mounts, connect both using
the same bolts.
Battery Enclosure
Channel holes: Drill
thru @.87 Dia.
Access hole for PV &
Luminaire harness to B.E:
Drill thru one side @ 1.25”
Dia. Approx. 4.25” below
top B.E. Channel hole.
28”
6” Min. from top of pole
Arm Mounting Hole
Drill thru 2x @.75”Dia.
Access hole for
Luminaire harness
Drill thru one side
@ 1.25” Dia.