All rights reserved
Shenzhen SOFARSOLAR Co ., Ltd.
C
21
All rights reserved
Shenzhen SOFARSOLAR Co ., Ltd.
C
22
Figure3-4 Moving the SOFAR 10-20KTL (2)
Step 2
Lift the SOFAR 10-20KTL from the packing case and move it to the installation position.
End
Step 1
To determine the position for drilling holes, level hole positions, and then mark the
hole position by using a marker, use the hammer dril to dril hole on the wall. Keeping the
hammer perpendicular to the wall, do not shake when drilling, so as not to damage the walls.
If the aperture errors, need to reposition.
Attention
To prevent device damag and personal injury, keep balance when moving
theSOFAR 10-20KTL because the SOFAR 10-20KTL is heavy.
Do not put the SOFAR 10-20KTL with its wiring terminals contacting the floor
because the power ports and signal ports are not designed to support the weight
of the SOFAR 10-20KTL. Place the SOFAR 10-20KTL horizontally.
When placing the SOFAR 10-20KTL on the floor, put foam or paper under the
SOFAR 10-20KTL to protect its shell.
3.6 Installing the SOFAR 10-20KTL
Step 2
The expansion screw is vertically inserted into the hole, pay attention to expanding
screw insertion depth (not too shallow).
Step 3
Putting the rear panel on the wall, the rear panel is fixed by the nuts.
Step 1
Step 2
Step 3
End
Step 4
Putting the SOFAR 10-20KTL hook on the rear panel.
Step 5
Using an M6 screw back and inverter bottom fastening, to ensure safety.
Step 6
Putting the rear panel and inverter to lock together, In order to ensure the safety (the
user can select lock according to the actual situation).
Step 4
Step 5
Step 6
SOFAR 10K~20KTL
User manual
SOFAR 10K~20KTL
User manual