5.3. Shutdown inverter
Step 1:
Turn OFF the AC circuit breaker.
Step 2:
Turn OFF the DC switch.
5.4. Setting power quality response modes
The setting and viewing method of power quality response mode and power grid
protection.
Once the power quality and grid settings have been selected at commissioning,
these settings will be locked, end customers cannot modify by themselves. These
setting require professional and technical personnel to conduct them by issuing
and transmitting instructions on the remote monitoring platform, on the premise
that the data acquisition rod is installed (WiFi/GPRS/Ethernet) . And the account
must be authorized by SOFARSOLAR.
Power quality settings can be set/view/changed by logging onto
solarmanpv.com.
Access to solarmanpv.com is restricted to authorised personnel only (refer
to Section 4.6 for instructions on accessing solarmanpv.com).
An account must be created to use solarmanpv.com.
Technical personnel can send control instructions on the monitoring page to
modify the mode and parameters of the machine, and the corresponding
instructions need to be provided by internal professionals.