15
5.
Guide the cable up under the large pulley towards the end of the safety dog.
Remove the 3/8” x 1 ½” shoulder bolt from the safety dog. Feed the shoulder bolt
through the collar of the safety release cable and then replace the shoulder bolt
securely to the safety dog.
NOTE:
Make sure shoulder bolt, 3/8” dia. x 1 ½” lg.
(6-0801), is lock tight to safety dog.
6.
Repeat step 2 for the power side tower.
7.
Guide the cable up under the large pulley and then over the small pulley towards
the safety dog. Wrap the cable around the thimble (attached to the safety dog with
a 3/8” x 1 1/2” lg. shoulder bolt) and then clamp it using two (2) wire rope clips.
Do not tighten fully at this stage.
8.
Adjust the cable length so that both safety dogs travel from full engagement position
to full release position when the safety release handle is pulled.
Tighten both wire
rope clips firmly when adjustment is completed.
Figure 12 – Safety Release Cable Routing and Adjustment
Summary of Contents for EELR326A
Page 8: ...7 5 2 BAY LAYOUT Figure 3 Bay Layout ...
Page 10: ...9 Figure 4 Safety Shut Off Bar Installation Figure 5 Safety Shut Off Bar Power Side ...
Page 24: ...23 8 PARTS MANUAL 8 1 LIFT ASSEMBLY ...
Page 27: ...26 8 3 HYDRAULIC SYSTEM ...
Page 29: ...28 8 5 POWER PACK 6 2055 AB 1381 208 230V 1PH 60Hz ...