16,000LBS 2-Post Lift
Installation, Operation and Maintenance
Page 7
EAZ0080V84A - Rev. 07/29/2021
Fig. 6 –
Overhead Assembly
26) Check idler column shimming. Use additional
shims (
see Fig. 5
) to remove any gaps that may
have been created while installing overhead
beam. Tighten anchor bolts and re-check column
for plumb. Torque to 150 foot-pounds.
27) Install Overhead Limit Switch to the Overhead
Beam using the rear set of holes on the Power
Side of the lift.
Fig. 7.
Fig. 7 – Overhead Limit Switch Power Side
28) Install the Idler Bracket to the Overhead Beam
using the rear set of holes on the Idler Side of
the lift.
Fig. 8. Note the orientation of the Idler
Bracket. The narrow slot needs to be facing
towards the Power Column.
Slide the Shutoff
Bar over the limit switch on the Power Side. Pin
the Shutoff Bar to the Idler Side Bracket with the
10mm dia. x 55mm Lg. clevis pin & hairpin
cotter.
Fig. 8 –
Overhead Bracket Idler Side
S
YNCHRONIZER
C
ABLES
29) Remove Cable Trapping Hardware at the top of
each column.
Fig 9.
Route free end of cables
coming out the top of the carriage up and over the
upper sheaves and back down the opposite side.
Do this for both cables and install the cable
trapping hardware.
Fig. 9 – Cable Trapping
INSTALLATION AID
INSTALL 1/2" HEX FLANGE BOLT
& NUT FOR SUPPORT OF
OVERHEAD. REMOVE AFTER
INSTALLATION.
COLUMN
EXTENSION
TABS
INSTALLATION AID
INSTALL 1/2" HEX FLANGE BOLT
& NUT FOR SUPPORT OF
OVERHEAD. REMOVE AFTER
INSTALLATION.
COLUMN
EXTENSION
TABS
INSTALLATION AID
INSTALL 1/2" HEX FLANGE BOLT
& NUT FOR SUPPORT OF
OVERHEAD. REMOVE AFTER
INSTALLATION.
COLUMN
EXTENSION
TABS
INSTALLATION AID
INSTALL 1/2" HEX FLANGE BOLT
& NUT FOR SUPPORT OF
OVERHEAD. REMOVE AFTER
INSTALLATION.
COLUMN
EXTENSION
TABS
INSTALLATION AID
INSTALL 1/2" HEX FLANGE BOLT
& NUT FOR SUPPORT OF
OVERHEAD. REMOVE AFTER
INSTALLATION.
COLUMN
EXTENSION
TABS
OVERHEAD
OVERHEAD
OVERHEAD
OVERHEAD
OVERHEAD