background image

16,000LBS 2-Post Lift 

Installation, Operation and Maintenance 

 

Page 6

 

 

EAZ0080V84A - Rev. 07/29/2021

 

L

OCK 

R

ELEASE

/P

AWL

 

Fig. 4 – 

Locking Pawl Assembly

 

13) Install the locking pawl, actuator, and spring (

Fig. 

4

).  Adjust air cylinder clevis to retract lock against 

inside of back of column when air cylinder is fully 
extended.    Tighten  air  cylinder  clevis  jam  nut 
against clevis. 

 

A

NCHORING

 

Note:  

  The anchor bolts must be installed at least 8” from 

any  crack,  edge,  or  expansion  joint.  Recheck  the 
area around both base plates. 

  Use a concrete hammer drill with a 3/4 inch carbide 

bit. Tip diameter should conform to ANSI Standard 
B94.12-1977 (.775 to .787). Do not use excessively 
worn  bits  or  bits,  which  have  been  incorrectly 
sharpened.  A  core  bit  may  be  necessary  if  an 
obstruction is encountered. 

Never substitute with 

shorter anchor.

 

14) Recheck “Inside of Columns” dimension (

Fig. 1

).  

15) Using  the  base  plate  as  a  template,  drill  one 

anchor hole. Drill through the floor if possible or to 
a depth of 5 inches minimum.  

16) Clean the hole inside and out. 
17) Assemble a washer and nut to the anchor with nut 

just below impact section of bolt. Drive the anchor 
into  the  hole  until  the  nut  is  3/4”  above  the 
baseplate (leaving room for shims). 

Complete  steps  15  thru  17  for  the  seven  (7) 
exposed  anchors  (one  at  a  time)  around  each 
column.  

18) Raise both carriages (400 lbs. ea.) high enough to 

drill the two inner anchor holes on each column. 

Measure both carriage heights to ensure they are 
in the same lock position.  

19) 

IMPORTANT

:

 

Place a safety support inside each 

column  as  a  backup  to  the  locks  since  the 
hydraulic  cylinders  are  no  longer  engaged  with 
the carriages. 

20) Repeat steps 15 thru 17 for the two (2) anchors 

under each carriage. 

21) Shim  both  columns  to  plumb  using  the  shims 

provided as shown in 

Fig. 5

. DO NOT shim more 

than 1/2" at any given point. Use a level no less 
than 24” in length to plumb columns. 

22) Drive all the anchors until nut and washer contact 

baseplate. 

 

Fig. 5 – 

Column Shimming

 

23) Tighten  Power  Column  anchors  and  recheck 

column for plumb. Re-shim if necessary. Torque 
to 150 foot pounds to set anchors. 

24) Loosen  Idler  Column  anchors  1/8”  and  proceed 

with the Overhead Beam installation. 

 

O

VERHEAD

 

25) Before raising overhead into position, install 4 (2 

per column) hex flange bolts and nuts in bottom 
hole  of  column  extension  tab 

(see  Fig.  6 

Installation  Aid)

  for  temporary  support  of 

overhead. Lift overhead assembly up into position 
and install with 8 (4 per column) 1/2-13 x 1” lg hex 
flange  bolts  and  hex  flange  nuts  per  side  as 
shown in 

Fig. 6

. For the wide position, the outer 

overhead holes will be used. For the 6” reduced 
width, use one set of outer overheard holes and 
one set of inner overhead holes. For the narrow 
width, use the inner sets of overhead holes.

 

Summary of Contents for EELS540A

Page 1: ...ation Maintenance Manual Two Post Surface Mounted Lift MODELS EELS540A EELS541A EELS743A EELS744A 16 000 LBS CAPACITY 4000 LBS PER ARM 309 Exchange Avenue Conway AR 72032 TEL 800 225 5786 IMPORTANT RE...

Page 2: ...loads equally distributed on all four arms Lifting and lowering speeds may vary depending on the weight of the vehicle A B F C E DRIVE ON DIRECTION 7 8 TO NEAREST OBSTRUCTION OR NEAREST WALL 19 REF 1...

Page 3: ...indoor use only with an operating ambient temp range of 5 40 C 41 104 F Outdoor installation is prohibited ELECTRICAL REQUIREMENTS For lift installation and operation it is necessary to have a dedicat...

Page 4: ...edition IMPORTANT Always wear safety glasses while installing lift TOOLS MINIMUM REQUIRED a Tape measure 16ft b Chalk line c 4ft level d 10 adjustable wrench e Standard open end wrenches 7 16 1 2 2 9...

Page 5: ...height Install the cable on the sheave and slide into place Stack the 3 8 spacer onto the sheave assembly Still holding the sheave assembly slide the pin into place Install the bolt to secure the pin...

Page 6: ...at a time around each column 18 Raise both carriages 400 lbs ea high enough to drill the two inner anchor holes on each column Measure both carriage heights to ensure they are in the same lock positio...

Page 7: ...et with the 10mm dia x 55mm Lg clevis pin hairpin cotter Fig 8 Overhead Bracket Idler Side SYNCHRONIZER CABLES 29 Remove Cable Trapping Hardware at the top of each column Fig 9 Route free end of cable...

Page 8: ...ared fitting off one full turn Again tighten flared fitting finger tight then rotate flared fitting 1 1 2 hex flats 90 deg 31 Mount Power Unit to power column as shown in Fig 11 The mounting hardware...

Page 9: ...wer Side Hose up the column to the lowest available hole of the column extension Insert steel tubing end of the Power Unit Hose into the extension outside in and connect to the tee Leave the assembly...

Page 10: ...dard Width and Height CL16 2 6 Reduced Height without Reduced Width CL16 2 6 or 12 Reduced Width without Reduced Height CL16 2 6 Reduced Height with 6 or 12 Reduced Width CL16 2 12 Reduced Height CL16...

Page 11: ...re the air line to the Idler Column using black wire ties through the double holes in the middle of the column Place the head of the wire tires inside the column Cut the air line to length and attach...

Page 12: ...ig 20 Fig 20 Adapter Rack Installation ELECTRICAL See Figure 21 for the following steps 64 Wire tie Limit Switch cord to Overhead hydraulic Hose and Power Unit Hose 65 Connect the Overhead Limit Switc...

Page 13: ...er rods The cylinders are shipped with a small amount of clear anti corosive lubricant that will be forced out through the wiper when the lift reaches full rise If lubricant is not wiped clean from th...

Page 14: ...16 000LBS 2 Post Lift Installation Operation and Maintenance Page 14 EAZ0080V84A Rev 07 29 2021 Fig 21 Electrical Wiring Diagram 2 T1 1 L1 3 A1 4 A2 LOAD INPUT Normally Open FIELD CONNECTIONS...

Page 15: ...that the lift inspectors are qualified and that they are adequately trained in the inspection of the lift The Owner Employer shall establish procedures to periodically maintain the lift in accordance...

Page 16: ...Test the stability of the vehicle by attempting to rock the vehicle Check adapters for secure contact with vehicle lift points If the vehicle seems unstable lower the lift and readjust the arms If th...

Page 17: ...clean Check for loose or broken parts Check hydraulic system for fluid leaks Check adapters for damage or excessive wear Replace as required with genuine Snap on Equip parts Check lock release activat...

Page 18: ...5 3 4 M6 x 14mm PHILLIPS PAN HEAD SCREW 8 B2065 4 4 M6 SERRATED FLANGE HEX NUT 9 B2065 5 1 CLEVIS PIN 10mm x 55 Lg 10 GJY12 3 1 HAIRPIN COTTER 11 12330 24 1 2 13NC HEX FLG HD C S x 1 Lg 12 12331 24 1...

Page 19: ...16 000LBS 2 Post Lift Installation Operation and Maintenance Page 19 EAZ0080V84A Rev 07 29 2021 PARTS BREAKDOWN continued Fig B Lock Power Idler...

Page 20: ...CK WASHER 29 37119 2 CLEVIS PIN KIT 30 37120 2 ROD END CLEVIS 31 37026 2 AIR CYLINDER 32 37041 2 SWIVEL ELBOW 1 8 PUSH LOCK 33 12088 2 EXTENSION SPRING 34 37042 2 CYLINDER PIVOT ROD 35 37031 4 5 32 SP...

Page 21: ...103 1 HYD TEE 54 12308 1 POWER UNIT HOSE ASSEMBLY 55 AB 81795 1 POWER UNIT SINGLE PHASE AD 81795 1 OPTIONA POWER UNIT THREE PHASE 56 31025 1 LINE CLAMP 57 40085 9 1 4 20 HEX FLANGE NUT 58 A2125 5 1 4...

Page 22: ...67 CL31020 8 WASHER 68 CL31021 4 1 3 8 RETAINING RING 69 12302 0 1 SYNC CABLE PACK 14 6 O A Ht 12302 2 1 SYNC CABLE PACK 16 6 O A Ht 70 40053 2 1 8 THICK BEARING 71 40774 S 2 SHEAVE SPACER 3 8 72 123...

Page 23: ...16 000LBS 2 Post Lift Installation Operation and Maintenance Page 23 EAZ0080V84A Rev 07 29 2021 PARTS BREAKDOWN continued Fig F Carriage 3 Stage Arms...

Page 24: ...T LOCK WASHER 89 12219 8 ARM SHIM 90 12205 8 5 16 24NF x 1 2 Lg SET SCREW 91 B2211 4 6mm x 30mm ROLL PIN 92 B2209 2 ADAPTER RACK 93 A1069 4 5 16 18NC x 1 HEX FLANGE LOCKING HEAD CAP SCREW 94 4100237 4...

Page 25: ...Z0080V84A Rev 07 29 2021 REVISIONS 06 18 2021 NEW PRODUCT RELEASE 07 19 2021 UPDATED IMAGES OVERALL INSTRUCTION AND PARTS BREAKDOWN 07 29 2021 ADDED STEP 55 UPDATED SPEC PAGE 08 30 2021 UPDATED SPEC P...

Reviews: