8.2
Installation of Rear Bolster Bar
Install the bolster bar to the rear end of both runways by using eight M24 Hex bolts, washers and
Hex nuts
located in the hardware kit. See
Figure 23.
Engine crane or floor jack will be required to lift and position the bolster bar. It may be necessary
to lower the lift to accommodate the installation.
Figure 23-Bolster Bar Installation
8.3
Installation of Transition Ramps
- Install the mounting bracket to the runways using hardware provided.
- Retain the transition ramps to the mounting bracket using the pin supplied.
- Ensure that both circlips are installed on either end of the pin.
Figure 24 – Transition Ramps Installation
M24 Hex Nut
9-0433 (8pcs)
Ø24 Flat Washer
9-0545 (16pcs)
M24 Hex Blot
9-0432 (8pcs)
Pin
9-0401
(2pcs)
Mounting Bracket
9-0398 (2pcs)
Transition Ramp 9-0402 (2pcs)
Ø25 Circlip
9-0417 (4pcs)
M12 Hex Bolt
9-0419 (2pcs)
Ø12 Spring Washer
9-0418 (4pcs)
Summary of Contents for EELR501A
Page 6: ...6 of 73 2 0 SAFETY WARNING DECALS...
Page 8: ...8 of 73 Figure 2 Lift Dimensions Side View Figure 3 Lift Dimensions Back View...
Page 18: ...18 of 73 Figure 12 Hydraulic Connections...
Page 33: ...33 of 73 Figure 31 Connection of Air Recoil Hose...
Page 64: ...64 of 73 16 6 Air Line Routing Map Figure 53 Air Hose Assembly...
Page 69: ...69 of 73 17 5 Console Labeling Figure 57 Console Labeling...