© SMP (PLAYGROUNDS) LTD, TEN ACRE LANE, THORPE, EGHAM, SURREY, TW20 8RJ
ZINGO X-012
Page 19
4.5
INSTALLATION
1)
Refer to site layout for position and orientation of product, then mark the outline of the position of the footings
with e.g. spray or chalk etc. Excavate the holes. See FIG.2 & FIG.3, 4 or 5 depending on type of unit to be
installed.
2)
Assemble to 2 off Straight Leg - 1200 deck (item 1), 2 off Clamp Rings (half) (item 44) and 1 off Deck Support
Casting (item 43) at the pre-inserted hole position for the 1200 high deck. See FIG.12 & 13.
i)
For assembly method see Note 4.4, 1), i) to iii) ensuring that the Deck Support Casting (item 43) is
slotted over one of the Clamp Ring (half) before assembling the second Clamp Ring (half).
3)
Assemble to 2 off Straight Leg - 1200 deck (item 1) 2 off Clamp Rings (half) (item 44) at the pre-inserted hole
position for the top clamp rail. See FIG.12 & FIG.A.
i)
For assembly method see Note 4.4, 1), i) to iii).
4)
Assemble to 2 off Straight Leg - 1200 deck (item 1) 2 off Clamp Rings (half) (item 44) at 600 position down
from the top clamp rail. Align Clamp Ring (half) radially to match with other rings on the post. See FIG.12 &
FIG.B.
i)
For assembly method see Note 4.4, 2), i)
5)
Assemble to 2 off Straight Leg - 1200 deck (item 1) 2 off Clamp Rings (half) (item 44) at 700 position down
from the 1200 Deck Clamp Height. Align Clamp Ring (half) radially to match with other rings on the post. See
FIG.12 & FIG.B.
i)
For assembly method see Note 4.4, 2), i)
6)
Assemble to 2 off Straight Leg - 1200 deck (item 1) 2 off Clamp Rings (half) (item 44) at 600 position up from
the previous Clamp. Align Clamp Ring (half) radially to match with other rings on the post. See FIG.12 &
FIG.B.
i)
For assembly method see Note 4.4, 2), i).
FIG.12
1
800
2900
1200 DECK
T
O
P CLAMP RAIL
FIG.13
44
1
53
72
74
44
43
74
CLAM
P HT
.
600
600
700
ISSUE B
Summary of Contents for ZINGO MAGIA X-012/P
Page 2: ...INTENTIONALLY LEFT BLANK ...