SERIES 28HE STEAM BOILER INSTALLATION AND OPERATION INSTRUCTIONS
9. Assemble the rest of the sections following steps 3
through 8 above.
10. Hydrostatically test the boiler by following the
instructions on page 7.
11.
While the boiler is being fi lled confi rm that all
of the draw rods are properly torqued and that
there are no leaks.
12. If any leaks are found tighten the draw rods on that
section until the leak stops.
Heat Transfer Rod Installation, Figure 7 (HE only)
The high effi ciency 28HE comes with design certifi ed
heat transfer rod sets. Each tube of 15 heat transfer rods
will baffl e one fl ue. In order to obtain the high effi ciency
for which the boiler was designed, the heat transfer rods
must be properly installed, Figure 7.
Figure 7 - Heat Transfer Rod Installation
Cleanout Cover Installation
1. The cleanout covers come insulated from the
factor y. Inspect the covers to ensure that the
insulation is not damaged or missing. If it is call the
Smith Customer Service Department.
2. Trim the 1/2 in. rope that’s sticking out around the
cleanout opening fl ush with the castings to insure an
air-tight seal, see Figure 5.
3. Install the cleanout cover bolts from the baffl ed side
of the cleanout cover and start the nuts, Figure 8.
4. Rotate the bolts so the cam heads fi t between the
cleanout cover bosses on the castings.
5. Insert the cleanout cover and tighten the nuts to
15 ft lbs
,
21 Nm
.
6. Apply a bead of high temperature silicone caulk
around the perimeter of the cleanout cover to
ensure an air tight seal.
Figure 8 - Cleanout Cover Assembly (Typical)
Burner Mounting Plate Installation, Figure 9
1. Apply two coats of the spray adhesive supplied with
the boiler to the rope groove on the plate. Allow time
for the fi rst coat to dry then apply the second coat.
When the second coat is tacky lay the 3/8 in. rope
into the rope groove and press in place.
2. Screw the four 7/16-14 in. x 2 1/2 in. studs into the
tapped holes in the boiler front section, Figure 9.
3. Install the burner mounting plate insulation block in
the burner opening in the front section of the boiler.
The small observation port cutout must be on the
top, left side.
4. Position the front jacket panel frame over the four
studs, Figure 9.