STEP 6:
Place barge flashings on roof at end of shed ensuring
the diagonal trimmed end is facing out.
Rivet the Barge Flashings to the roof and the side wall,
using four rivets on top of barge and four into the side
(
fig.3
).
fig.1
fig.3
X 4
X 4
Barge
STEP 3:
Ensure shed is sitting level and square.
Beginning from the left hand end (looking from front) centralise the Roof sheets on the Ridge Beam.
Ensure that the Roof is tight against the Gable Wall Sheets. Nail 1 x 40mm Weatherseal nail through the Pan into
the Ridge Beam.
At the back left hand corner, (from front) line up the ribs on the Roof Sheet with the ribs on the Wall Sheet then
using 1 x 40mm Weatherseal nail, fix Roof Sheet through the pan into the Top Plate. Repeat at the front
.
ROOF ASSEMBLY CONT...
12
STEP 4:
Centralise the Roof at the right hand end with the Ridge Beam.
Using 3 x Weatherseal nails, fix roof sheet to the Ridge Beam and front & back
Top Plates.
Ensure that the Ridge Beam is straight, Nail roof sheets to ridge beam at each
overlap, through the pan using 6 x Weatherseal nails.
Ensure the Front and Back Top Plates are straight. Nail the roof sheets to the
front & back Top Plates, using 1 x nail per pan (
fig.1
).
fig.2
SIDE
WALL
FRONT WALL
BACK
WALL
SIDE
WALL
TOP PLATE
BOTTOM PLATE
RIDGE BEAM
STEP 5:
Rivet the 2 ridge flashings together using 4 rivets,
so total flashing is 3.050m long. Rivet the Ridge
Flashing to the centre of the roof using 8 x rivets
as shown (
fig.2
).
STEP 7:
Place spouting in position and rivet to Barge Flashings at
each end and rivet to roof sheets (1 rivet per 1 sheet).
Repeat with remaining spouting.