7 Commissioning
SMA Solar Technology AG
Installation Manual
EDMM-WAGO-IO-IA-en-11
44
Figure 37: Example configuration: temperature input
6. Fill out the input fields and confirm with [
Save
].
7. Select the
Instantaneous values
menu item in the
Monitoring
menu and check the information entered. The newly added
channel should now appear in the list and display the current
values.
7.3.4
Defining the channel and scaling for grid management services
One analog input channel should be created as the setpoint for the active power limit [% of the nominal PV system
power] and one analog output channel should be created as the actual value of the power at the point of
interconnection [W].
Summary of Contents for Modbus EDMM-10
Page 54: ...www SMA Solar com...