95
mm
1250 mm
1330 mm
1480 mm
1335 mm
A
B
C
755 mm
1300
mm
265 mm
1300
mm
1250 mm
1330 mm
265 mm
A
B
1165
mm
2155
mm
2250
mm
Figure 20: Position of the support feet of the service platforms
Position
Designation
A
Support feet of the work platform in front of the inverter compartment
B
Support feet of the work platform in front of the MV transformer compartment
C
Support feet of the work platform in front of the medium-voltage switchgear compartment*
* Only folded out temporarily
The service platforms are included in the specification of the minimum clearances.
Local regulations for hand rails must be observed. Hand rails for the service platforms are not included in the scope of
delivery of the product and must be provided on-site.
Open Areas below the MV Power Station for Internal Arc Pressure
The open areas below the MV Power Station must not be blocked by any other installations or groundfill. The only
permissible exception is the oil spill containment. The areas underneath the MV Power Station are needed for inverter
ventilation and pressure dissipation in the event of arc faults.
4 Information for Installation
SMA Solar Technology AG
Transportation and Installation Requirements
27
MVPS22JP-TA-en-20
Summary of Contents for MEDIUM VOLTAGE POWER STATION 1000-1SC-JP
Page 38: ...www SMA Solar com...