5 LCS Tool
SMA Solar Technology AG / SMA Solar Technology America LLC
16
IMVIOBOX-IA-xx-11
Installation Manual
Figure 5.8 LCS tool - list of all inverters connected to the Inverter
Manager
12. If sufficient PV power is present and the grid code
conditions are met, the inverters are connected to the
grid.
13. During commissioning it is possible to download a
commissioning report in the
Reports
menu. The report
contains information about inverter settings, including
actual disconnection values for each inverter.
See figure 5.9.
Figure 5.9 LCS tool - commissioning report