6 Commissioning
SMA Solar Technology AG
System Manual
SPBusiness-SH-en-10
19
6
Commissioning
6.1
Information on Commissioning Support and Warranty
Commissioning support:
A commissioning support is included in the system. You have the option of receiving on-site or
telephone support for commissioning of SMA Solar Technology AG.
If you would like to use the support, contact Service (see Section 7, page 28). For the
commissioning support on site, you will receive an order form from SMA Solar Technology AG. Fill
out the order form and send it to [email protected]. After receipt of the order form, you will
receive an appointment confirmation from SMA Solar Technology AG.
Warranty:
In order to obtain the system warranty of ten years, the commissioning report for the system must be
completed in Excel and e-mailed to
as an
Excel file. To complete the commissioning report, you will need the serial numbers of all
components in the system. The commissioning report can be found in the download area at
www.SMA-Solar.com.
6.2
Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
always perform in the prescribed order.
Configuration of the overall system
The SMA Inverter Manager is the device for the configuration of the storage system via the
LCS-Tool. The SMA Data Manager is the superordinate unit for the configuration of the overall
system.
• Only configure the storage system via the SMA Inverter Manager. Use the LCS-Tool for
this.
• After commissioning, the parameters of the PV inverters and of the SMA Data Manager
can be adjusted via the Sunny Portal powered by ennexOS. The parameters of the batter
inverter can be set via the LCS-Tool.
Procedure
See
1.
Configure the Janitza UMG 604-PRO.
2.
Commission the battery inverter.
3.
Commission the battery.
4.
Commission the PV inverters (optional).