Section 4 – Inspections Before Operation
4.1 Operator’s Responsibility
Do these tasks before each work shift and in this
sequence:
1. Visual and daily maintenance inspections
(refer to
Section 4.2
).
WARNING
Do an inspection on the MEWP for damage or
loose or missing parts. If damage is found, lock
and tag the MEWP and remove it from service. If
you do not obey, there is a risk of death or serious
injury.
2. Function tests
(refer to
Section 4.3
).
Refer to
Section 4.4
for a checklist of the inspection
items.
WARNING
If the MEWP is damaged or has been modified
from the initial factory-delivered condition, without
permission from Skyjack, lock and tag the MEWP.
Remove the MEWP from service. If you do not
obey, there is a risk of death or serious injury.
Repairs to the MEWP are tasks only for a qualified
service technician. Do the visual and daily
maintenance inspections and function tests again
after the repairs.
Scheduled maintenance inspections are a task only
for a qualified service technician.
Summary of Contents for SJ12
Page 1: ...OPERATION MANUAL VERTICAL MAST 213721AAA September 2019 ANSI CSA SJ12 SJ16...
Page 4: ...4 SJ12 SJ16 213721AAA Notes...
Page 8: ...8 SJ12 SJ16 213721AAA Notes...
Page 14: ...14 SJ12 SJ16 213721AAA Notes...
Page 20: ...20 SJ12 SJ16 213721AAA Notes...
Page 58: ...58 SJ12 SJ16 213721AAA Notes...
Page 64: ...64 SJ12 SJ16 213721AAA Notes...
Page 80: ...80 SJ12 SJ16 213721AAA Notes...
Page 82: ...82 SJ12 SJ16 213721AAA Notes...
Page 83: ...Cancer and Reproductive Harm https www p65warnings ca gov WARNING...
Page 84: ...www skyjack com...