Chapter 2: Install the server hardware
16
Chapter 2: Install the server hardware
This section contains the following topics:
•
About electrostatic discharge
•
Unpack the shipping carton
•
Install the server enclosure in a rack
•
Mount the enclosure in the rails
•
Connect the network cables
•
Connect the power cables
•
Organize the cables
•
Power on the system
•
Attach the OmniCube bezel
Installing the server hardware involves unpacking all hardware components, installing the enclosure in
a rack, connecting the power and network cables, and powering on the server.
About electrostatic discharge
You must protect sensitive hardware from electrostatic discharge (ESD), which can damage electronic
components.
■ Ensure the server hardware is fully grounded at all times to prevent damage from electrostatic
discharge.
■ When not installed in a rack, server hardware must be stored in its original packaging or placed on a
sturdy surface that is protected from electrostatic discharge.
■ When handling server hardware components, always use the electrostatic wrist strap provided, or
use a similar form of ESD protection.
Unpack the shipping carton
You unpack the shipping carton to prepare the system hardware components for installation.
Before you begin
■ The OmniCube servers are heavy. You must have at least one other person to help you lift and
unpack the carton, and SimpliVity recommends the use of a datacenter equipment lift.
■ You have cut the pallet shipping straps, which might have considerable tension, using an appropriate
tool and safety wear.