Shielding and Protective Earthing
1.9.1 Shielding
Normally, shielded cables are strain-relieved directly after the cabinet/rack entry and then
grounded on a large-surface screening rail installed for this purpose.
1.9.2
Protective Earthing / Grounding
When installing a SICAM AK 3 system, attention is to be paid, that the cabinet or rack used,
features a proper protective earthing / grounding. That means, that all electrical conducting
parts must be connected large-surface and as short as possible with the existing grounding
system.
Summary of Contents for SICAM AK 3
Page 8: ...Open Source Software 8 SICAM RTUs SICAM AK 3 User Manual Edition 07 2016 DC2 028 2 03 ...
Page 84: ...Installation 84 SICAM RTUs SICAM AK 3 User Manual Edition 07 2016 DC2 028 2 03 ...
Page 166: ...System Components 166 SICAM RTUs SICAM AK 3 User Manual Edition 07 2016 DC2 028 2 03 ...
Page 180: ...Prepare Engineering 180 SICAM RTUs SICAM AK 3 User Manual Edition 07 2016 DC2 028 2 03 ...