CM EIB
Manual, 03/2010, J31069-D1262-U002-A4-7618
19
Commissioning
5
5.1
Commissioning steps
Prerequisite
●
BUS and power supply must be present.
Procedure
1.
Connect the PC via the serial EIB interface.
2.
Start ETS.
3.
Configuration of the application program in the ETS.
4.
The application program is loaded via the EIB interface in the nodes. The application
program is available on the LOGO! homepage (http://www.siemens.com/logo).
5.
Click "Program Physical Address" in the ETS.
6.
Press the "Prog ↓" button on the CM EIB to switch the CM EIB to programming mode.
The "BUS" LED glows orange.
NOTICE
The "Prog ↓" button must not be pressed too hard. This could damage the device. If a
contact is present, the LED glows orange.
7.
The LED stops glowing when programming of the physical address is complete. You can
now indicate the physical address on the unit.
Composition of physical address:
Area /
Line / Node
XX
XX
XXX
1.
You can now install the application program.
The device is then ready for operation.
2.
If several CM EIB are installed in an EIB system, steps 1-9 must be repeated for each CM
EIB.
Note
Please refer to the corresponding EIB/KNX documentation for further details regarding
EIB installation.
Summary of Contents for Logo! CM EIB
Page 1: ...Communication with LOGO on the EIB according to the Konnex standard Manual Edition 03 2010 ...
Page 2: ......
Page 12: ...Application planning 2 3 Storage CM EIB 12 Manual 03 2010 J31069 D1262 U002 A4 7618 ...
Page 14: ...Installation 3 1 Installation CM EIB 14 Manual 03 2010 J31069 D1262 U002 A4 7618 ...
Page 18: ...Connecting 4 2 Connecting the EIB CM EIB 18 Manual 03 2010 J31069 D1262 U002 A4 7618 ...
Page 24: ...Service and maintenance 6 3 Disposal CM EIB 24 Manual 03 2010 J31069 D1262 U002 A4 7618 ...
Page 42: ...Functions 7 4 EIB communication CM EIB 42 Manual 03 2010 J31069 D1262 U002 A4 7618 ...