34
8024250/18HT/V2-0/2020-12| SICK
O P E R A T I N G I N S T R U C T I O N S | ZIRKOR200 Ex-G
Subject to change without notice
5
INSTALLATION
5.7
Storage information
SICK devices and spare parts must be stored in a dry place with sufficient ventilation. Paint
fumes, silicone sprays etc. must be avoided in the storage environment.
5.8
Scope of delivery
Check the scope of delivery according to the order confirmation/delivery note.
Checking the delivery state
Check all components have no exterior damage.
Make sure the supply voltages indicated on the type plates correspond to the system
conditions.
5.9
Installation
Installation steps overview
DANGER: Health hazard due to contaminated measuring probe
Depending on the composition of the gas in the measuring channel, the analyzer unit,
after use in the process, may be contaminated with substances that can cause serious
damage to health.
▸
Decontaminate the analyzer unit before storage.
▸
Wear the specified protective clothing for all work with a contaminated analyzer unit.
▸
Clean all components of the measuring system with slightly moistened cleaning
cloths. Use a mild cleaning agent here.
▸
Pack all components for storage or transport. Preferably use the original packing.
▸
Store all components of the measuring system in a dry, clean room.
Storage temperature for all components -40 °C to +80 °C.
Step
Procedure
Reference
1
Fit the counter flange on the duct.
see “Fitting the counter flange on the
duct”, page 35
2
Fit the control unit.
see “If necessary, attach duct insula-
tion to protect the device from heat.”,
page 35
3
Install the control unit.
see “Installing the control unit”,
page 35
4
Fit the analyzer unit.
see “Fitting the analyzer unit”,
page 36
5
Fit the analyzer unit with cooling protection pipe.
see “Fitting the analyzer unit with
cooling protection pipe”, page 38
6
Install the analyzer unit.
see “Installing the analyzer unit”,
page 38
7
Align the V-shield.
see “Aligning the V-shield”, page 39
8
Lay connection cable.
see “Laying the connection cable”,
page 40
9
Install connection cable.
see “Installing connection cables”,
page 41
10
Fit the pneumatic unit.