7
Commissioning
7.1
Preparatory commissioning
Commissioning for preparatory purposes and under laboratory conditions differs in
some respects from commissioning in the target system.
In general, all safety and hazard warnings applicable to mounting (
) and electrical installation
see "Important notes", page 16
must also be
observed under laboratory conditions. In addition, further notes must be taken into con‐
sideration to guarantee the most effective preparation possible:
•
Only connect those devices to the product that you want to configure or program.
•
Operate the connected device in a controlled and contained network environment
for the time being to check network communication if necessary.
•
Note the company standards that apply to the use of checking and testing devices.
•
For initial programming, use ideal conditions for sensor or camera recognition.
•
Use the largest possible deviations from these ideal conditions to check the pro‐
gramming with respect to its error tolerance and reliability, and to determine error
limit values.
Procedure
1.
Place the device on a non-slip base.
2.
Connect the required peripheral devices,
see "Connecting peripheral devices",
.
3.
Connect the network connection.
4.
Connect the voltage supply.
5.
Switch on the voltage supply.
7
COMMISSIONING
22
O P E R A T I N G I N S T R U C T I O N S | SIM1000 FXA
8023299//2019-03-13 | SICK