48(61)
3. Installation and Debugging
Read this chapter carefully before installation of the machine. Install the
machine by following steps.
Power supply should be fixed by qualified technicians!
3.1 Installation Steps
1) Put the main body of the machine at a proper place and connect it with power
supply.
2) Install material hopper onto the dryer and connect it with signal wires from the
main body.
3) Use steel wire hose to connect the suction mouth of vacuum hopper to the
relative suction mouth of dust-suction main machine, in turn connect the
suction mouth of dust-suction main machine to the suction mouth of vacuum
hopper.
4) Connect high pressure air pipe with air supply (pressure at 5~6kgf / cm
2
).
3.1.1 Power Supply
SAL-UGP series should be connected to 3
Φ
, 400V, 50 / 60Hz power and earth.
Make sure main switch is turned off before you connect the power.
Summary of Contents for SAL-10HP-UGP
Page 1: ...SAL UGP Series Vacuum Powder Loader Date Apr 2013 Version Ver B English ...
Page 2: ......
Page 28: ...28 61 2 3 Electrical Diagram 2 3 1 Main Circuit 400V Picture 2 7 Main Circuit 1 400V ...
Page 29: ...29 61 Picture 2 8 Main Circuit 2 400V ...
Page 30: ...30 61 2 3 2 Electrical Components Layout 400V Picture 2 9 Electrical Components Layout 400V ...
Page 37: ...37 61 2 3 4 Main Circuit 230V Picture 2 10 Main Circuit 1 230V ...
Page 38: ...38 61 Picture 2 11 Main Circuit 2 230V ...
Page 39: ...39 61 2 3 5 Electrical Components Layout 230V Picture 2 12 Electrical Components Layout 230V ...