Thank you for installing this charge point.
Make sure there is enough space to properly do the work.
Ensure to work safely and take the safety of others into
consideration as well, always work according local
safety regulations.
When selecting the mounting location of the charge
point, make sure that future maintenance work can be
done easily.
5.1 PREPARATION
Step 1: Prepare the cabling & RCD and MCB (conform to
local rules & regulations)
Step 2: Indicate which circuit(s) the charge point is
connected to the distribution board
Step 3: Turn the socket lid anti-clockwise and out of the
cover of the charge point
Step 4: Then pull the cover from the rear edge to open the
charge point. Do not use any objects or tools to do this.
5.2 MECHANICAL MOUNT
For standard wall mount proceed with 5.2a, for optional
pole mount on pavement proceed with 5.2b, for optional
pole mount in soil proceed with 5.2c.
5.2A MECHANICAL MOUNT (WALL)
Step 1: Attach the wall bracket at the desired height (+/-
1 m height) on the wall
Step 2: Put the charge point on the wall bracket to
check its placement. On the wall, mark the positioning
of the bottom two attachment points of the charge point
and select the appropriate fixtures (plugs, screws and
washers)
Step 3: Ensure that the grey spacers are placed on the
back of the charge point at the bottom two attachment
points
Step 4: Secure the charge point to the wall bracket using
the two M8 x 12 mm bolts and washers provided
Step 5: Secure the charge point to the wall using the
bottom two attachment points.
5.2B MECHANICAL MOUNT (POLE ON
PAVEMENT)
Step 1: Drill holes into the pavement for the wedge bolts
or chemical anchors (not provided)
Step 2: Route the power cable(s) and UTP cable(s)
through the pole
Step 3: Mount the wedge bolts or chemical anchor into
the pavement
Step 4: Mount the pole to the threaded ends with
washers and nuts (not provided)
Step 5: Mount the green/yellow pole earthing wire to the
terminal block earthing connection
Step 6: Secure the charge point to the pole bracket
using the four M8 x 12mm bolts and washers provided,
making sure to connect the pole earthing wire to the
bottom right bolt.
5.2C MECHANICAL MOUNT (POLE IN SOIL WITH
CONCRETE BASE)
Step 1: Dig the concrete base into the soil, make sure it
is steady and level
Step 2: Route the power cable(s) and UTP cable(s)
through the pole
Step 3: Mount the pole to the concrete base with the 4
bolts M8 x 35 and washers that are provided
Step 4: Mount the green/yellow pole earthing wire to the
terminal block earthing connection
Step 5: Secure the charge point to the pole bracket
using the four M8 x 12 mm bolts and washers provided,
making sure to connect the pole earthing wire to the
bottom right bolt.
5.3 POWER CONNECTION
Step 1: Select the appropriate grommet(s) that suits
the cable(s) thickness and place it in the opening of
the power cable inlet. Lubricate if necessary to make it
easier to feed the power cable through
Step 2: Secure the power cable(s) using the cable
clamp(s)
Step 3: Mount the (closed) black grommet in the
remaining cable inlet to make the charge point watertight
Step 4: Connect the power to the terminal blocks, like
indicated in the ‘3.4.1 Overview of Connections’ section.
5. INSTALLATION PROCEDURE