background image

14' End Wall

DETAIL 'D'

Step 14A

Assemble Gable Frame

1.

Cut a 16' long 2x4 to a length of 14'-2".

2.

Gather (2) 62-1/8" long and (2) 69-7/8" long 2x4s. Place blue marked ends of 69-7/8" 2x4s

together at the ridge. Position 62-1/8" boards as shown below. Set the 14'-2" long 2x4 on edge
and nearest to 14' end wall. The gable frame when complete will be 2" wider than loft floor.

3.

Check the frame for squareness. Measure from the knee to the corner of the 14'-2" long 2x4.

Measure again from opposite knee. The measurements should be the same, see Detail 'C'.

4.

It is important that both gables and the trusses are built the same. Temporarily tack 1x4 blocks,

included in the kit, to the loft flooring around the gable frame members, see above. The blocks
measure 8"-12" long and may have angled ends.

5.

Screw the 2x4 plate to the truss leg with (2) two 2-1/2" deck screws on each end. See Detail 'D'.

DETAIL 'C'

1x4 Block

69-7/8" Long 2x4

62-1/8" Long 2x4

Position This 2x4 on Edge. See Detail 'D'

62-1/8" Long 2x4

14'-2" Long 2x4

83-3/8" Overall Height

162-5/8" (+ or -)

14'-2" Long 2x4

62-1/8"

Long 2x4

Blue Ends

Together

Summary of Contents for the Pinewood

Page 1: ...ot be copied in whole or in part without consent from Reynolds Building Systems Inc Copyright 2020 Assembly Book Manufactured by Reynolds Building Systems Inc 205 Arlington Drive Greenville PA 16125 S...

Page 2: ...t floor walls and loft floor are completed Framing lumber for the first floor walls and loft floor exterior siding loft flooring roof sheathing and a 32 pre hung six panel steel door with lock will be...

Page 3: ...th of floor joists Shorten joist measurements if necessary to obtain 14 0 building width 7 Install 10 ten floor joists between the 12 joist headers Secure with 16d galv deck nails Constructing Details...

Page 4: ...runners Stagger the 2x6 blocks to make it easier to nail the block between the joist 4x4 11 It is important that the floor be level and square Measure the floor diagonally corner to corner Then measur...

Page 5: ...r and indicate with X marks where the wall studs will be located 96 Top Wall Plate 96 Treated Bottom Plate 24 23 1 4 24 The length of pre cut wall studs will vary from 92 1 4 to 93 depending on your l...

Page 6: ...Top Wall Plate 96 Treated Bottom Plate 24 23 1 4 26 2 Install 5 five pre cut wall studs between the top and bottom plates Nail the treated bottom plate to each wall stud with 2 two 16d galvanized dec...

Page 7: ...together and indicate with X marks where the wall studs will be located 12 0 Top Wall Plate 12 0 Treated Bottom Plate 24 23 1 4 24 2 Install 9 nine pre cut wall studs between the top and bottom plates...

Page 8: ...ether and indicate with X marks where the wall studs will be located Mark an S on bottom plate where the door header supports will be located See drawing below 2 Install 8 eight pre cut studs over the...

Page 9: ...indicate with X marks where the wall studs will be located Step 5 Assemble a 13 5 Long End Wall Frame Treated Bottom Plate Pre cut 2x4 Wall Studs 2 Install 9 nine pre cut wall studs between the top a...

Page 10: ...be located See drawing below 2 Assemble the front wall frame using the wall plates cut above and install 6 six pre cut wall studs over the X marks 3 Cut 2 two pre cut studs to a length of 82 Install o...

Page 11: ...Brace center frames with pre cut studs 13 5 Wall Frame 1 Erect a 8 long wall frame on the back side of the floor IMPORTANT make sure frames are square and plumb 3 Butt a 12 long wall frame to 8 frame...

Page 12: ...the front wall 8 Locate 2 two 13 x 48 siding panels Install siding above the door opening with bottom edge 3 4 below door header If necessary cut top flush with other siding panels 9 Install the rema...

Page 13: ...hen installed 5 Repeat to install joist headers on the opposite end of the building Step 10 Install 2x8 Joist Headers on Back Walls 1 Cut a 12 long 2x8 board to 139 Install this 2x8 to the 8 back wall...

Page 14: ...ilding 1 Install joist hangers on all 2x8 joist headers over the X marks flush with the bottom of the 2x8s Use 1 1 2 hanger nails Joist Hanger Step 11 Install 2x8 Floor Joist 2 Cut a 2x8 14 to 161 and...

Page 15: ...lush with the top of the loft flooring Install all trim using 6d galvanized box nails spaced 12 apart 1x4 Trim 1 1 2 x 10 Filler Depending on the pre cut stud length and if the siding extends below th...

Page 16: ...he 14 2 long 2x4 Measure again from opposite knee The measurements should be the same see Detail C 4 It is important that both gables and the trusses are built the same Temporarily tack 1x4 blocks inc...

Page 17: ...x4 plate using 2 two 10d sinker nails See Detail E DETAIL E 62 5 8 Stud 70 5 8 Stud 7 8 S t u d 3 1 2 x 8 Gusset Framing Square 3 1 2 x 8 Gusset 3 1 2 x 8 Gusset 7 Attach 36 gable stud using a 2 1 2 l...

Page 18: ...sting the gable frame on these boards will make it easier to install the siding 3 Install a 12 x 44 1 2 siding panel that has a tongue edge Install the siding with the cut edge flush with the side of...

Page 19: ...2x4 12 Step 16 Install Gable 2x4 12 Brace 2x4 Block DETAIL F 4 Nail bottom edge of siding to 1x4 trim with 6d galvanized nails spaced 12 apart 5 Erect gable on the opposite end Siding Extends Over Tri...

Page 20: ...en an 8 long 2x6 Cut last board to fit 2 Repeat on front wall 1 Lay truss parts inside the 1x4 blocks used around gable frames One end of the 70 3 8 long 2x6 boards have a blue mark Place these ends t...

Page 21: ...g Install the hangers using 6d common nails 5 Remove the 2x4 12 boards used to brace the gable As you progress setting trusses tack these boards to keep trusses plumb Don t remove the 2x4s until the r...

Page 22: ...extend 3 8 past the corner trim on the end wall Use 6d galv nails 2x4 Block 1x4 Corner Trim on End Wall 4 Space 6 Cut an 8 long 1x4 trim board to fit between the soffit board and the bottom of the sid...

Page 23: ...48 20 3 4 x 96 20 3 4 x 48 2 Locate 2 two 48 x84 OSB sheets packed in our kit and cut to a length of 75 3 Make certain the trusses and the gables are plumb Starting from front left end install 7 16 O...

Page 24: ...he vertical cut located at the peak of the gable Install 1x6 flush with the top of the roof sheathing Use 6d galv nails spaced 12 apart 2 Install 75 1 4 long 1x6 white pine trim boards at the side of...

Page 25: ...will serve as a door stop when the doors are closed Use 6d galv nails spaced 12 apart 1x6 Keystone 48 1 2 Door Trim 84 LP Door Jamb 3 Install 2 two 1x4 84 3 4 long trim boards flush to the sides of th...

Page 26: ...trim to allow room for the doors to expand due to humidity 4 Determine position of hinges and install to side trim with 2 screws 5 Install the window using the short white screws 6 Install door handl...

Page 27: ...long 1x3 trim boards along each side of the window flush with the top frame Note the front flange projects above the window frame creating a slot for the trim The top trim will rest on the side trim T...

Page 28: ...8 Truss Top Cord 4 ea 2x6 x 62 1 8 Truss Leg 2 ea 2x4 x 48 Pre built Soffit 4 ea 24 x 9 Truss Ridge Gusset 8 ea 24 x 14 1 2 Truss Knee Gusset 4 ea H 1 Metal Truss Hangers 6 ea 2x8 Metal Joist Hangers...

Page 29: ...2 x 44 1 2 2 3 8 LP Wall Siding 48 x 13 2 7 16 OSB Sheathing 48 x 84 4 7 16 OSB Sheathing 48 x 72 2 7 16 OSB Sheathing 48 x 27 2 7 16 OSB Sheathing 27 x 51 2 7 16 OSB Sheathing 20 3 4 x 51 2 7 16 OSB...