7
INSTALLATION
Unpack and Inspect Material
IR-SNIF-1,2,3 Package:
The IR-
SNIF-1,2,3 package contains the
following material:
1.
IR-SNIF-1,2,3 Single Zone
Monitor
2.
Installation and Operation
Manual
3.
Hose barb fittings and 10
micron tube end filters
(one hose barb and filter
for each inlet – two of
each are provided)
4.
CTS/Warranty form to be
completed and returned to
Sentech
Optional Purchases:
The IR-SNIF-
1,2,3 package may also contain the
following material:
1. Plastic FRPE tubing, ¼ inch
OD for sample tube
2. Combination
Horn/Strobe
alarm
3. Horn alarm
4. Strobe alarm
Other Required Material:
The
following material is required but not
provided by SenTech:
1. Primary power wiring
2. Wiring for connection to alarm
devices or other building
systems
3. Relay contactors for building
system loads greater than 5
amps
4. ¼
inch
tubing
(if
not
purchased from SenTech, or if
copper tube is required by
local code
If any material is missing, or appears
to be damaged, contact Sentech
Corporation for assistance.
Identify Location for Monitor,
Sample Points and Alarms
Monitor Location:
ASHRAE-15
specifies that the refrigerant monitor
is to be located in the mechanical
room. There are two interpretations
of this: the unit itself is to be
installed in the mechanical room; or
the sample point is to be located in
the mechanical room. Because the
IR-SNIF-1,2,3 is an active air draw
monitor, it can be installed nearly
anywhere in the vicinity of the area
to be monitored.
If local codes allow, the monitor can
be installed at the entrance to the
mechanical room, with the sample
tube routed into the mechanical
room and the fresh air reference
routed to an appropriate location. If
the monitor is located outside the
mechanical room, a fitting should be
installed and an exhaust tube routed
either into mechanical room, or
outdoors. If it is routed outdoors, it
must not be located near the fresh
air reference.
If local codes require the monitor to
be
physically
installed
in
the
mechanical room, it should be
installed in the best location for ease
of use and routing of sample and
fresh air tubing. If the monitor is
installed in the same room as the
Summary of Contents for IR-SNIF-1
Page 50: ...47 05 20 2008 ...