7-17
NOTES:
•
A MICROWAVE ENERGY TEST MUST ALWAYS BE PERFORMED WHEN THE UNIT IS SERVICED FOR
ANY REASON.
•
MAKE SURE THE WIRE LEADS ARE IN THE CORRECT POSITION.
•
WHEN REMOVING THE WIRE LEADS FROM THE PARTS, BE SURE TO GRASP THE CONNECTOR, NOT
THE WIRES.
B. CHECKOUT PROCEDURES
(1) CHECKOUT PROCEDURES FOR FUSE BLOWING
CAUTION: REPLACE BLOWN FUSE WITH 20 AMPERE FUSE.
Fuse blows immediately after
the door is closed.
Fuse blows immediately after
the door is opened.
Fuse blows when the door is closed and START
key is touched.
Improper operation of the primary interlock, secondary
interlock switches and/or the interlock monitor switch.
Malfunction of the high voltage transformer; the high
voltage capacitor including the diode, the magnetron,
the blower motor or the circuit board.
PROBLEMS
CAUSES
NOTES:
•
If the fuse is blown by an improper switch operation, replace all switches and the fuse at the same time.
After replacing the defective switches with new ones, make sure that they are correctly connected.
•
Check for microwave energy leakage according to INTERLOCK ADJUSTMENT PROCEDURES on page
7-11 when the primary interlock, secondary interlock switches and/or the interlock monitor switches are
adjusted or replaced.
Summary of Contents for 721. 63762
Page 9: ...5 1 SCHEMATIC DIAGRAM OVERALL CIRCUIT DIAGRAM...
Page 10: ...5 2 MATRIX CIRCUIT FOR TOUCH KEY BOARD...
Page 37: ...8 2 CONTROLLER PARTS I 1001 W171 W171 2016 2009 2007 2017 EV...
Page 38: ...2004 2008 2002 2006 W106 2381 8 3 CONTROLLER PARTS II EV...
Page 40: ...8 5 LATCH BOARD PARTS 4000 W102 4001 4002 4003 4002 4004 EV...
Page 44: ...8 21 SCHEMATIC DIAGRAM OF P C B...
Page 45: ...8 22 PRINTED CIRCUIT BOARD...