INSTALLATION
MANUAL
Product:
Document #:
Rev:
Page:
SEAKEEPER 9 / 7HD
90222
6
1 of 2
Section 4: STARTUP
4.0 Introduction
This section describes the first startup of the Seakeeper.
Also reference Seakeeper Document # 90223, Seakeeper 9 / 7HD Operation Manual.
Previous sections for mechanical, electrical and cooling installation must
be completed before this startup sequence is initiated.
Before continuing, covers must be installed unless the Seakeeper is
inaccessible and there is no risk to injury. Also, the area around the
Seakeeper must be clear of personnel and equipment.
4.1 Startup Instructions
1) Energize 24 VDC supply at the customer supplied electrical disconnect.
2) Supply 208-230 VAC to Motor Drive Box at customer supplied electrical disconnect.
3) If sea water pump for the Seakeeper is not supplied though cable from Motor Drive Box,
t
urn on the boat’s AC or DC dedicated circuit breaker that supplies power to the sea
water pump.
4)
With system powered up check the display for any ALARMS. If there are any ALARMS
present they must be corrected first.
5) Press the Seakeeper ON/OFF Button on Display.
The RED LOCK ICON and the
PROGRESS BAR will appear and be RED until the Seakeeper is at speed, then
stabilization can begin.