INSTALLATION
MANUAL
Product:
Document #:
Rev:
Page:
SEAKEEPER 9 / 7HD
90222
6
2 of 3
Section 5: INSTALLATION CHECKLIST AND SUPPLIES
Cable 3 (Seakeeper supplied)
– Connect female end of CAN communications
Cable 3 to mating connector on the Seakeeper
wire harness
–
Route CAN communications Cable 3 from the
Seakeeper to helm (male end goes to helm)
– Connect male end of CAN communications
Cable 3 at helm to CAN Tee Adapter
– Connect Display and Seakeeper supplied Cable
4 to CAN Tee Adapter with CAN Terminator
Cooling Checklist (reference Installation Manual Section 3)
Verify coolant level in heat exchanger coolant reservoir.
Connect sea water hoses / open sea cocks to heat exchanger and test sea water
pump.
Verify 4 GPM (15 LPM) minimum and 8 GPM (30 LPM) maximum sea water flow
through heat exchanger under all operating conditions of the boat.
Startup Checklist (reference Installation Manual Section 4 & Operation Manual Sect. 2)
Remove lifting bolts and Install cover panels
Turn on 24 VDC circuit breaker
Turn on 230 VAC circuit breaker
Verify display works and no alarms are present
1. If display does not work, turn off both circuit breakers immediately
2. Check polarity of 24VDC power per Section 2.2.5
Follow instructions in Section 4.1 of Installation Manual to turn on the Seakeeper
Verify sea water pump turns on when the Seakeeper is turned ON
Verify that no ALARMS are present
Follow instruction in Section 4.1 of Installation Manual to turn off the Seakeeper
AC & DC power and sea water pump may be turned off after the Seakeeper is
turned off by placing the Seakeeper in LOCK mode and Turning the Seakeeper off
Seakeeper 9 takes 4+ hours to coast down to zero rpm from full speed