NOTES
The electrical installation and the operation logics must comply with current regulations. Keep the power cables (motors, power
supply) separated from the control cables (push-buttons, photo-eyes, radio, etc.). Separate conduits should be used to prevent
noise issues.
Note:
Use “cable clips” and/or “duct/box pipes” fitting close to the control panel box so to protect the interconnection cables
against pulling efforts.
Note:
The beam is not equipped with movement inversion system in case of obstacles. To respect the laws EN 12453 and EN
12445 it is recommended to insert external disposals into it.
INTENDED USE
VELA system has been designed exclusively for the automation of barriers.
SPARE PARTS
The spare parts orders must be sent to:
SEA s.r.l. Zona Ind.le, 64020 S.ATTO Teramo Italy
SAFETY AND RESPECT FOR THE ENVIRONMENT
We recommend not to spoil the environment with product and circuit packing material.
CONFORMITY REQUIREMENTS
VELA automation system complies with the following standards:
(Machine Directive)
(Electromagnetic Compatibility Directive)
(Low Voltage Directive)
2006/42/CE
2004/108/CE
2006/95/CE
English
Sistemi Elettronici
di Apertura Porte e Cancelli
International registered trademark n. 804888
®
To the attention of users and technicians
12) Release system
To release operate as follwos
- Turn the protection cap of the lock.
- Insert the key into the same and turn it about 180° into anti-clockwise
direction until the beam is released (Fig. 18).
- Open manually the beam.
To re-lock operate as follows
- Turn the key into clockwise direction until it’s blocked. (Fig. 19).
- Extract the key in vertical position.
- Re-close the protection cap.
Fig.18
Fig.19
180°
PERIODICAL MAINTENANCE
Check the functionality of the release
Lubricate the bearing of the balance
Check the efficiency of the spring
Check the beam fixing screws and the balance and the casing
Check the integrity of the connexion cables
Check and eventually adjust the efficiency of the By pass valves
Annually
Annually
Annually
Annually
Annually
Annually
All above mentioned operations must be executed exclusively by authorized installers.
INITIAL CHECK AND PUTTING IN SERVICE
After having completed all necessary operations, for the correct installation of the product VELA, described in the present manual
and after having valued all resting risks which could arise in whatever installation
is necessary to test the automation to
guarantee the max. security
and in particular way to guarantee the respect of what foreseen by the law and the normatives in
force. In particular the test must be executed following the
EN12445
ruel which establishes the testing methods for the testing of
the gate operators respecting the established limits by the
EN 12453 law.
Cod. 67410035 Rev 06 - 06/2010
25