Figure 11
3.1.1 Tools needed for Installation
Please make sure that the tools listed below are available for installation.
3.1.2
Operator
components and their installation
Figure 12 shows an example installation with cable management including all possible components. Cables
for accessories are not included.
Figure 12
1.
3.2
Mains Connection (Power Supply)
The mains connection may only be carried out by a qualified person. The connection of the control box is via a 3-
wire cable. Carefully read the assembly instructions for the gate
operator
before proceeding. Make sure that the
cables are properly layed and and properly inserted to prevent cable breakage. The arrangement of the
accessories should therefore be predetermined.
3.2.1
Note on the power supply connection
2.
The electrical installation and connections for the gate operator may only be carried out by a qualified electrician.
The supply line for the
gate operator
must be equipped with an
over-voltage
fuse.
Before all electrical work, the
system must be de-energised. Safeguard the system against being switched on again without
authorization
.
8