15
221873B
7.1 Flue Position and Length
Determine flue application, length and terminal position before
starting.
Refer to diagram 7.1.
Note: The Easyfit Top Outlet Flue Pack and the Extended Top
Outlet Flue Pack contains a flue duct extension piece complete
with "O" rings, this should be discarded.
If you are using a Flue Bend or a Vertical Flue Kit, please follow
the instructions supplied with the kit.
To make a neat finish to the flue outlet a flue collar kit, part No.
443286, with instructions, is available, see diagram 7.2.
Note: If required an optional wall liner kit, part no. 900862, is
available complete with instructions.
7.2 Flue Assembly
Extend the telescopic flue to the required length, making sure
that the minimum overlap is no less than 25mm, and that the flue
terminal projects 15mm minmum beyond wall face, see diagram
7.1.
Carefully drill though air duct pilot hole and secure with self
tapping screw provided in fittings pack, see diagram 7.1.
Seal the joint with the tape provided.
If the flue system requires the addition of flue extension kits,
drill, seal and secure them with the self tapping screw and tape
provided.
Note: Should any one of the flue sections require cutting to
obtain desired flue system length, cut at the end opposite the
expanded end.
If the boiler is not to be fitted for some time cover the hole in the
wall.
7.3 Internal Access Flue
If access to the outside wall is not practical, the flue system can
be installed from inside. Use of the optional wall liner kit is
required.
7.4 Rear Outlet Flue Fixing
Fit the self adhesive foam seal provided in the flue pack around
the air duct at the position shown in diagram 7.1.
Make good around the flue outside after installation of the boiler.
Important: If the wall liner kit is used, the self adhesive foam seal
included in the wall liner kit must be used in place of the one
supplied with the flue pack, see diagram 7.3 for position of self
adhesive seal.
7.5 Top Outlet Side or Rear Flue Fixing
Make good the area around the flue inside and outside after
installation of the boiler.
Important: If the wall liner kit is used, the self adhesive foam seal
included in the wall liner kit must be used in place of the one
supplied with the flue pack, see diagram 7.3 for position of self
adhesive seal.
7.6 Flue Positioning
Push the flue assembly into and through the hole such that it is
within the wall, and does not stick out into the room. Do not push
the flue assembly too far into the hole as it has to be pulled back
into the boiler and secured
Diagram 7.2
7148
OPTIONAL
FLUE
COLLAR
Diagram 7.3
FOAM SEAL
FOAM SEAL
WALL THICKNESS-
OVER 300mm
15mm
WALL THICKNESS-
UP TO 300mm
Q-35mm
Q
Q
7102
WITH WALL LINER KIT ONLY
7 Flue Preparation