9. Commissioning & Recommissioning
Installer reference guide / Mono tank integrated type
172
9.1 Overview
This chapter explains what you have to do and know to commission the system after it is installed and configured.
9.2 Precaution
NOTE
• When starting the unit for the first time, it is expected that the power consumption exceeds the stated
standard power consumption.
This is caused by the new compressor that needs about 50 hours of cumulative running hours before
reaching a stable (lower) power consumption.
• Always operate the unit with the switches and sensors in the correct places. Failing to do so, may result
in damaging the compressor and or the electronics.
• Only operate the unit with the outlet water temperatures within range of the specifications 15>Tw2 < 70,
if needed preheat via BUH/BSH.