Final Check and Trial Operation
To complete the installation, perform the following checks and tests to
ensure that the air conditioner operates correctly.
Check the followings:
•
Strength of the installation site
•
Tightness of pipe connection to detect gas leak
•
Electric wiring connection
•
Heat-resistant insulation of the pipe
•
Drainage
•
Grounding conductor connection
•
Correct operation (follow the steps below)
1. Press the
Power
button and check the following:
The indicator on the indoor unit lights up.
1. Turn on the air conditioner and select Cool mode to run the compressor for 3 minutes.
2 . Release the valve caps on High and Low pressure side.
3 . Use L wrench to close the valve on the high pressure side.
4 . Approximately 2 minutes after, close the valve on the low pressure side.
5 . Stop operation of the air conditioner.
6 . Disconnect the pipes.
3. Press the
Air swing
button and check the following:
4. Press the
Power
button to stop the operation.
2. Press the
Mode
button to select Cool or Heat mode.
In Cool mode, use
Temp +
or
-
button and set the temperature at 16°C.
In Heat mode, use
Temp
+
or
-
button and set the temperature at 30°C.
Cooling mode (indoor unit check)
Inlet air temp. - Outlet air temp : From 10°C to 12°C( indicative delta T)
Heating mode (indoor unit check)
Outlet air temp. - Inlet air temp : From 11°C to 14°C (indicative delta T)
Pump down procedure (when removing the product)
•
Approximately 3~5 minutes later, outdoor unit will start to operate and the Cool or Warm air will blow out.
•
After 12 minutes of stationary condition check the indoor unit air treatment:
•
When you complete the installation successfully, hand over this manual to the user for storage in a handy and safe