26
EB 8111/8112 EN
Measures
4.4 Preparation for installation
Proceed as follows:
Î
Flush the pipelines.
The plant engineering company is responsi-
ble for cleaning the pipelines in the plant.
Î
Check the valve to make sure it is clean.
Î
Check the valve for damage.
Î
Check to make sure that the type desig
-
nation, valve size, material, pressure rat
-
ing and temperature range of the valve
match the plant conditions (size and
pressure rating of the pipeline, medium
temperature etc.).
Î
For steam applications, make sure that
the pipelines are dry. Moisture will dam
-
age the inside of the valve.
Î
Check any mounted pressure gauges to
make sure they function.
Î
When the valve and actuator are al
-
ready assembled, check the tightening
torques of the bolted joints (
u
AB 0100).
Components may loosen during trans
-
port.
Note
Summary of Contents for 3321
Page 11: ...EB 8111 8112 EN 11 Safety instructions and measures...
Page 27: ...EB 8111 8112 EN 27 Measures...
Page 33: ...EB 8111 8112 EN 33 Mounting and start up...
Page 35: ...EB 8111 8112 EN 35 Operation...
Page 45: ...EB 8111 8112 EN 45 Servicing...
Page 53: ...EB 8111 8112 EN 53...
Page 55: ...EB 8111 8112 EN 55 15 11 12 16 2 5 1 4 13 17 14 63 62 5 2 8 Type 3321 DN 65 to 100 NPS 2 to 4...