10-2
EB 2540 EN
Decommissioning
To decommission the regulator for service
work or disassembly, proceed as follows:
1.
Close the shut-off valve (1).
2.
Depressurize the plant.
3. Completely drain the pipelines and
valve.
4. If necessary, allow the pipeline and reg-
ulator components to cool down or warm
up to the ambient temperature.