17
| DOC9063L
Ocean Master 1000
4 INSTALLATION AND START-UP
4.1 Securing the pump
4.2 Connections to the pump
• Check for foreign objects in the pump and physical damage on pump
• Gaskets to be handeled with highest degree of caution
• Gasket and sealing surfaces must be cleaned before assembly
DOC1627544
A
A
DOC1627544
DOC1627544_1
A
B
DOC1627544_1
Installation requirements must be observed, otherwise there is a risk of damage
The pump must be installed on a stable foundation, which must
be level and stable, so that the pump is not twisted or exposed
to a profile distortion.
The pump must be installed with M16 bolts on all four legs,
which must be tightened to 180 Nm
(A).
Immediate before connecting the pipes, remove protective covers.
The M12 bolts must be tightened with 60 Nm (B).
In order to prevent tensions in the pump, the pipe connections (A) must be
tensionless while tightening the bolts.
4.3 Connecting the service liquid
The service liquid must be connected to the pump at the hose connection, see
illustration.
DOC1627543_1A
DOC1627543_1A